Brick plinth on a strip foundation: plinth construction and step-by-step do-it-yourself installation instructions


The base of a house is a structure made of building material, which is a transitional element from the foundation of the building to the load-bearing walls and is their basis.

Its main function is to separate the foundation of the house, which lies in the ground and is exposed to low temperatures, from the load-bearing walls, which are designed to retain heat indoors.

It also prevents the penetration of atmospheric moisture and surface storm water through capillaries up the wall. Appearance is also very important, because a building with a high base looks much more impressive and massive.

DIY brickwork: tools, order and features

Now that you have an idea of ​​how to lay bricks with your own hands, you need to talk about the procedure as well as some technical nuances.

Sample list of tools for bricklaying

Let's start with the tool. You will need:

  • mason's trowels - apply and level the mortar onto the bricks;
  • concrete mixer or container for mixing mortar;
  • mortar shovel - for kneading and periodic mixing;
  • two or three buckets for the solution;
  • plumb line - check the verticality of walls and corners,
  • building level - to check the horizontality of the row of masonry;
  • cord-mooring - for beating rows;
  • jointing (for molding seams);
  • hammer-pick for breaking incomplete bricks (halves, 3/4 and checks - 1/4);
  • The rule is a flat metal or wooden strip to check the plane of the wall.

Next we will talk about the features of the technology. First: it is advisable to soak the brick before use. This is especially true in hot, dry weather. Then it will “pull” less moisture from the solution. If there is not enough moisture, the cement will not be able to gain the required strength, which will affect the strength of the building.

First, two corners are driven out, then they are connected with several rows of brickwork

Second: the corners are driven out first. First the first two. They are connected with 2-3 rows of bricks according to the chosen masonry pattern. Then the third corner is kicked out. The second and third are also connected in several full rows. Afterwards the fourth corner is placed and the perimeter is closed. This is how walls should be built, going around them around the perimeter, and not pushing walls out one by one. This is one of the most common mistakes.

Third: there are two row control technologies. The first is that nails are inserted into the seams of the corners, to which strings are tied. It needs to be pulled so that it marks the top edge of the brick, and also limits the outer (and, if necessary, inner) surface of the wall.

Procedure for attaching the mooring cord

The second way is to use wooden or metal orders. This is a flat strip or corner on which marks are applied every 77 mm - marks on wood or cuts on metal. They mark the required row thickness: brick height + seam. They are installed using flat mounting brackets that are inserted into the seam. If necessary, they are then simply removed and rearranged higher.

There is another way - a mason's corner. It has a slot on one side, into which there is a solution at an angle.

Breaking out a row using a mason's corner

The disadvantage of this method is the same as just using a nail in the seam: the height of the row must be controlled “manually” when drawing out the corners. If you lack experience (and where can you get it if you are doing bricklaying with your own hands for the first time), this is difficult. Having (having done it yourself) everything is easier.

Fourth: preparation of incomplete bricks. As you have seen, when laying, they use halves, three-quarter bricks and checks - 1/4 parts. To ensure that the work does not slow down, it is necessary to prepare them before starting masonry. This is done using a hammer-pick. When preparing, high precision in size is required, otherwise the dressing will go wrong. To make it easier to control the length, marks of the appropriate length are made on the handle. By placing the pen on the brick, marks are made on both sides of the spoon. Then, placing a pickaxe blade on the mark, they hit the reverse side with a hammer, making notches. Having made notches on both spoons, they break the brick with a strong blow of the pick.

Types of socles

This is determined by the location of the front wall of the plinth in relation to the façade:

  • speaker This option is used when it is necessary to increase the load-bearing capacity of the base. In this case, the element is extended two to three centimeters beyond the wall plane. There is a drawback - you will have to take measures to remove rain moisture flowing down the building;
  • sinking. The façade wall hangs over the basement. It is best to use this option when durable building materials that do not require additional finishing were used to make the base;
  • in one plane. The base part and the wall are in the same plane. This method is rarely used and mainly on outbuildings of secondary importance. The finishing layer is made of one material.

There are no specific requirements for the height of the basement - everything is determined by the presence of the basement and the foundation itself.

Ground floor price

The price of the basement floor is determined by summing up several types of costs:

  • costs for cleaning the area;
  • costs for developing a trench, removal and disposal of selected soil;
  • costs for arranging a drainage system - its production is necessary if a high level of groundwater is detected;
  • costs of installing a high-quality waterproofing layer on the foundation;
  • work on reinforcement, setting formwork and pouring concrete;
  • costs for the purchase of building materials.

On average, for comparison, the price of the basement is a third of the total cost of furnishing the entire house. Tentatively, we can assume that the price of building a basement floor is in the range of 18,000 – 21,000 rubles per square meter.

Step-by-step instructions for laying a plinth

Step 1. Calculate the required amount depending on the width and height of the masonry. Take the approximate quantity data from the table.

How many bricks are needed for 1 m3 of base.

Dimensions of bricks Quantity, seam parameters are not taken into account Quantity including seams

Standard size

512 394

One and a half brick size

378 302

Double size

242 200

If you are working with bricks of non-standard sizes, you will have to independently calculate the volume of the base and divide it by the volume of one brick. The calculations are not complicated; there is no need to describe them.

Foundation plinth

Step 2. Check the horizontalness of the foundation strip. If the foundation was made by responsible builders, then the deviation from the horizontal at the corners of the structure will not exceed two centimeters; such a spread can be easily eliminated without additional operations during the preparation of the base of the first row of the plinth. You need to check the horizontalness of the foundation using a water or laser level. Are there significant deviations found? You'll have to straighten the tape.

  1. Secure level slats at the corners of the foundation in a vertical position. The sizes are arbitrary, there is no need to take long ones.
  2. Beat off a horizontal line on one of them, transfer the value of the horizontal line to the second staff.
  3. Pull the rope according to the marks, do not allow it to sag. Measure the distance between the rope and the foundation plane along the entire length of the tape. This way you can estimate the approximate amount of work and calculate the amount of materials.
  4. If the unevenness exceeds 2 centimeters, you will have to prepare a concrete mixture; the spread is smaller - you can use ordinary cement-sand mortar. One condition - during the manufacture of the material, increase the amount of cement, it should be at least three parts to one part of sand.
  5. Place the finished solution on the surface of the foundation tape and level it along the stretched rope. The work can be done by eye; in the future, the bricks of the base will be installed according to the level and all flaws will be eliminated.
  6. It will take at least two weeks to harden. If the weather is very hot and dry, then the solution should be moistened generously with water at least three times a day.

Do not rush to start laying the plinth right away; strictly adhere to the recommended technology.

Step 3. Place two layers of roofing felt on a flat strip to waterproof the bricks

This is very important, without waterproofing the base will quickly collapse

Roofing felt insulation

Step 4. You need to start laying by laying two corners. The technology depends on how many bricks are in a row in width. You can lay corners from one, one and a half, two, two and a half and three bricks. If you do not have experience in producing such work, then practice. First lay the bricks without mortar, then work with mortar. The movements should become automatic; during training, constantly use control tools. Be sure to bandage, alternate spoon and butt rows. Now that you have experience, place the corners directly on the foundation strip. The height of the corners is 5–7 bricks. To begin with, the height is enough, so it is easier to control the correctness of the masonry and timely correct possible deviations in the position of the base.

Chain ligation system for laying the plinth

Step 5. At the height of the first row of each corner, drive in nails and pull the rope. Make sure that the rope lies exactly on the edges of the bricks. At this point, the preparatory work on laying the corners of the plinth is completed; start working on the straight sections.

Basement brickwork

Brick plinth laying

Laying the plinth

Leveled brick of the basement row

Further work on the base is no different from work on the wall; the rows are constantly being bandaged. If you use clinker bricks for external surfaces, use them only on the visible side.

Beginner mistakes

Construction level and masonry

Prices for building levels

Construction levels

The base is a very important element of the structure and the only one that cannot be repaired. Even problems with the foundation can be solved; there are special technologies for strengthening it. True, this will take a lot of time and is expensive. If the base begins to collapse due to incorrect calculations, then nothing can be corrected. We focus on this not with the goal of scaring developers, but with the goal of forcing them to very carefully follow all the recommendations of professionals and technologies that have been proven over the years. We will try to answer a few questions that novice masons often ask.

Is it possible to lay a mortar more than one centimeter thick to level the base? This need arises most often on foundations made of reinforced concrete blocks. Only competent specialists under the guidance of an experienced foreman can correctly install foundations from such materials. He must constantly monitor the position of each block using a professional level. If the variation in height does not exceed 2–3 centimeters, then it can be eliminated with a solution. But be sure to use a metal reinforcing mesh with a wire diameter of at least 5 mm. No plastic materials will withstand the load on the base; they are only suitable for plastering walls.

Masonry with reinforcement

Laying out the solution

Is it possible to use bricks made without firing for the base? It is possible, but not advisable; we have already discussed this issue above. But if you really need to put these bricks somewhere, then they can only be placed inside the base; all sides must be covered with ceramic bricks. Accordingly, they can only be used on plinths with a width of at least two bricks, otherwise it is impossible to make the correct binding and fulfill the described condition.

Use quality brick

In what cases can you do without leveling the foundation strip with concrete mortar? This is a rather difficult technology, let’s look at it in detail.

Prices for cement and basic mixtures

Cement and base mixtures

  1. At each corner of the foundation, the foreman taps (shoots) the values ​​by which the upper plane of the base must be raised. These measurements are made with a level. For example, on one corner of the foundation it is written +12 cm, on the second +20 cm, on the third +15 cm, etc. Such marks are made on all areas of the foundation on which the floor slabs should lie, in these places the base should face zero mark – floor level. Of course, the wide variation in the height of the foundation tape indicates that it was made by outright hacks.
  2. Develop a preliminary plan for reaching the desired height. You need to start from the corners, then all the rows are aligned along them. Make a plan to solve the problem in advance. If, for example, you need to raise the height of the plinth by 15 cm in two rows, then this cannot be done using mortar alone. Place approximately 2.5 cm on the foundation with the obligatory use of metal reinforcing mesh; the upper beds of bricks are equal to the pure mass. There are cases when it is necessary to use bricks of different thicknesses; you will have to purchase them additionally. It is prohibited to use bricks split with a hammer throughout the entire thickness for the plinth; they can only be cut on a special machine with a diamond disc and water cooling.
  3. After all the corners are made taking into account the measurements, begin laying the rows, using a stretched rope to control the position. Let’s say right away that such work is difficult, and we do not recommend that beginners do it. It’s better to invite a professional for a few days, he will lay out the corners, and it will be easier to work on them.

What types of socles are there?

Types of base

Depending on the position of the front surface in relation to the facade wall, the plinth can be:

  • speakers. It is used if it is necessary to increase the load-bearing characteristics of the base; the plane of the element protrudes several centimeters beyond the plane of the wall. Disadvantage - it is necessary to take special measures to drain rainwater coming from the walls;
  • sinking. The facade wall hangs over the plinth. It is recommended to use in cases where the base is made of durable building materials that do not require finishing;
  • in one plane. The facade wall and plinth are located along the same line. This option is rare, most often on unsatisfactory outbuildings. The finishing of the façade and plinth is done using the same materials and using the same technology, or is not done at all.

What should the height of the plinth be? There are no special requirements, it all depends on the availability and purpose of the basement and the horizontalness of the foundation strip. If the building does not have basements and the strip is smooth, then there is no need to make a special base. As for the advice “at least 50–60–70” and so on centimeters, you should not pay attention to them. The final decision is made only taking into account the architectural features of the building.

How high should the plinth be made?

And one last thing. Do not forget to leave vents in the plinths for natural ventilation of the underground space. If, of course, the house design provides for their presence.

Basement brick performs both aesthetic and protective functions

Types of base

During the construction of the basement, it is allowed to use bricks that have already been used previously. It is worth noting that this material must be durable. This will ensure the durability of the entire structure as a whole. Thus, two main tasks are solved:

  • costs for new brick are reduced;
  • Solid material of high quality is used.

Next, it’s worth talking about plinths, when the process of finishing the walls has already been completed, and it itself is insulated

This note is of particular importance, since during the work the relative position of structural parts may change. There are three main types of plinth made of brick that can be filled

Thus, it is worth highlighting the following varieties:

  • protruding relative to the walls;
  • sinking;
  • located flush with the wall.

As for the first type of base, this design provides for a protective drain. This is due to the fact that such a structure is highly exposed to precipitation. Therefore, masonry requires the use of only high-quality materials. This type of construction, as well as the one that involves placing a brick plinth at the same level with the wall, is used quite rarely today.


Before laying begins, the corners should be set correctly.

Recessed masonry is used for load-bearing surfaces made of gas silicate blocks. This foundation prevents rain from getting into the joint under the wall. It will go underground, and the waterproofing layer will be provided with reliable protection from external influences. There is also an opportunity to save money that will be spent on construction. It should be noted that when building a house, the base becomes sinking only after insulation with foam plastic and plastering of the walls.

Recommendations for choosing bricks for the plinth

As mentioned above, our recommendations do not apply to residential buildings; they should be built only according to the project, and in it all the requirements and parameters of the bricks are indicated. Let's consider cases of choosing a brick for a plinth only for non-residential buildings and outbuildings. What characteristics should you use to select materials?

Frost resistance

Frost resistance of bricks

Bricks, depending on the brand and manufacturing technology, have this indicator from F15 to F100 or more. This means that the material can withstand 25–100 freeze/thaw cycles at maximum humidity. And moisture permeability ranges from 2% to 12%. State standards regulate the minimum period of natural wear and tear of buildings; it is equal to 50 years. If an F50 brick is dipped into water fifty times and then exposed to frost, it will lose approximately 30% of its original strength, which is considered a critical value. But the basement brick will never become completely wet; it is always plastered or protected with other coatings. In practice, F50 brand brick lasts much more than fifty freeze/thaw cycles.

Frost resistance - the number of freezing and thawing cycles during which the stone will retain its original strength

Why do bricks lose strength during freezing/unfreezing and what does this depend on? During freezing, water increases in volume by about 10%, and the forces of ice are so great that no known building material can withstand them. The more water there is in the brick, the more microcrystals of ice there are in the brick, the faster the destruction occurs.

Thickened ceramic brick 250*120*88 mm, M-150, F 50

Strength

Determined according to GOST 530-2007, the grade of brick for laying load-bearing walls must be at least M125; with a safety margin, designers recommend using grade M150 brick for plinths.

Bricks made from many materials and using various technologies are suitable for these indicators, but some of them cannot be used in conditions of high humidity.

How bricks are made

Let's look at one example. Mark M100 means that the brick can withstand a load per square centimeter of at least 100 kg and no more than 125 kg. The surface area of ​​a standard brick is 25 cm×12 cm = 300 cm2. One brick of the M100 brand is designed for a load of at least 30 tons.

Solid brick M100

We have provided the calculation so that you can more clearly imagine what forces different brands of bricks can withstand. Of course, these values ​​​​provide that the load is evenly distributed over the entire surface (bed), in practice this rarely happens due to the presence of air pockets in the masonry.

Brick sides

What types of bricks can be used for the plinth?

NameBrief performance indicators

Ceramic solid

Water absorption ≤ 12%, strength ≥ M100, frost resistance no less than F50. Used most often, universal application. The front surface must be protected from the negative effects of precipitation.

Ceramic hollow

Water absorption ≤ 16%, strength ≥ M150, frost resistance no less than F50. used for plinths of light buildings without reinforced concrete floor slabs. The outer surface must be plastered with cement-sand mortar or lined with durable materials. Afraid of mechanical damage.

Clinker

Water absorption ≤ 5%, strength ≥ M250, frost resistance no less than F100. It surpasses ceramic samples in all technical parameters. When laying a plinth, it is recommended to use two or more bricks wide as the outer face row. The surface of the base of this option does not need to be additionally finished with various building materials. The disadvantage of clinker bricks is their high cost.

Now, having an idea of ​​the requirements for the plinth and the technical parameters of the bricks, you can consciously select specific materials and begin laying the element.

Base

Usually the base of the house is laid out of the same brick from which the foundation was made. Sometimes it is possible to use sand-lime brick for the base of the foundation, but this is not recommended. You can line the walls and base with brick, then you need to take this into account when laying the foundation and expand it by about 12 cm - this is the standard thickness of facing bricks.

The brick for facing the foundation is a special facing or clinker brick. Which brick is better for the plinth, everyone decides for himself; both of these options are durable and have all the properties of building bricks, and look beautiful. The cladding can be connected to the walls in different ways; see how to do this in the video.

Kinds

Types of brick basement structures:

  • smooth. The identical thickness of the wall and the permanent structure is observed. Improving the aesthetics of the external design of the facade is achieved by decorative borders or cornices. Achieve a visual distinction between the foundation and the building;


Smooth

  • protruding façade of the base. It is distinguished by its effectiveness, a clear distinction between the base and the structure. Low tides are required;


Speaker

  • sinking. Due to the aggressive influence of precipitation on the surface of the base, a sinking type of structure is provided. Recommended for areas with frequent, heavy rainfall. The basement wall is thinner than the foundation.


Sunken

Features of the brickwork of the plinth

It is important to be careful about the step-by-step execution of work and to do everything in the established order. This will make it possible to obtain a high-quality structure

The corners of the building are set: bricks are placed along the width of the planned structure

It is important to use a level to ensure the angles are positioned accurately. Once the position is established using a level, the bricks do not move. Then measure the sides and diagonals of the surface: they should be equal

This makes it possible to establish the correctness of the placement of the bricks. The maximum error can be 2 cm. Correct installation of corners affects the strength of the house.


There are a number of nuances when laying bricks

Brickwork during the construction of different stages of the building has its own subtleties:

  1. The brick for the plinth is placed on a solution of cement and sand: in it, one part of cement corresponds to three parts of sand.
  2. The thickness of the basement structure is determined by the material that will be used for insulation. When using foam plastic, the thickness should not be more than 38 cm.
  3. Usually the masonry is made in 2 bricks, this technique is optimal. Don’t forget about the thickness of the planned walls. It is not recommended to lay out the base thicker than the walls. Then water can accumulate at the junction of the base and walls, which will lead to accelerated destruction of the room.
  4. When laying out, you can use different bricks. The choice depends on the installation. Either a whole brick or its halves can be used. When laying, it is recommended not to forget about the ventilation holes; they should be at a distance of 2 meters from each other.
  5. It is recommended to reinforce the masonry every 2-4 rows; for this purpose, a 5*5 cm mesh is used.
  6. In relation to the walls, the base can be flush or recessed. It is better to prefer the second option, this will prevent moisture from entering from the walls.

Waterproofing and insulation


When using waterproofing, the base does not absorb moisture.
If you lay the brick directly on concrete, the base will absorb liquid during operation. This is dangerous and can lead to structural failure. Therefore, great attention must be paid to waterproofing measures. Roofing felt is often used for this purpose. This material combines accessibility and durability. Before laying the brick, the strip is lined with 2 layers of insulation, and between them is coated with bitumen mastic. To protect the masonry itself, it can be covered with a special film or treated with a painting compound.

To insulate the structure, polystyrene foam boards and expanded clay are widely used. You can also use an adhesive composition that does not contain sorbent and acetone. When performing installation, you need to ensure that there are no gaps. If they do appear, they should be sealed with mineral wool or polyurethane foam.

Brick plinth laying technology

Laying bricks on the surface of the foundation must be carried out taking into account certain rules, which will ensure the high quality of the created structure.

Preparing the necessary materials


Brick laying on the plinth

The solution must be prepared immediately before performing the main work. It must be used within 3 hours as it quickly hardens and loses its properties. The preparation of cement-sand mortar can be done in a concrete mixer or done manually.

Take a basin of a suitable size and fill it with sand and cement (4:1), using a special mortar shovel. After mixing the dry ingredients, add water and 2-3 drops of liquid soap (this will give the solution additional plasticity). All ingredients are thoroughly mixed to obtain a mixture with a homogeneous consistency.

Experts recommend pre-soaking the brick in plain water for 15 minutes. Laying such material will be much easier and will allow you to easily eliminate minor defects that appear during work. After pre-soaking the material, seams are obtained that will be much stronger than usual. This is achieved by the absence of penetration of capillary moisture from the solution into the masonry.

Brick laying technology

For high-quality bricklaying, use the following instructions:


Types of bricklaying

  • First, the corners are set, which should be at the same level. A cord is stretched between them for laying the next bricks.
  • The solution for the bottom row is applied directly to the roofing material, spread with a trowel so that it does not reach the edges by 2-3 cm.
  • The thickness of the seam is usually 12 mm, and with reinforcement it reaches 16 mm (metal mesh is used).
  • The corner is formed from two bricks laid at right angles. For reliable fixation, use a construction hammer.
  • Excess solution is removed with a trowel. It is applied to the side faces of red brick to form vertical seams.
  • The position of each brick is checked using a level and plumb line.
  • All masonry elements are carefully pressed to the surface, which ensures the reliability of the created structure.
  • The bricks at the corners are laid several rows higher, which allows a cord to be pulled between them to form the entire masonry.
  • During work, the quality of masonry corners is checked with a square, level and plumb line.

Acceptable errors:

  • in the vertical plane up to 10 mm;
  • in horizontal – 5 mm.

If small defects are detected, they can be eliminated by varying the thickness of the seam. But if the differences in level are large, it is impossible to get rid of them in this way

Therefore, in the process of laying each row, it is necessary to pay due attention to each brick. Particular care must be taken in forming corners, which affect the quality of the entire structure.

Related video: How to lay bricks correctly

https://youtube.com/watch?v=sGE2TKsrNjs

Selection of questions

  • Mikhail, Lipetsk — What discs should I use for cutting metal?
  • Ivan, Moscow - What is the GOST for rolled sheet steel?
  • Maxim, Tver - Which racks for storing rolled metal products are better?
  • Vladimir, Novosibirsk — What does ultrasonic processing of metals without the use of abrasives mean?
  • Valery, Moscow - How to forge a knife from a bearing with your own hands?
  • Stanislav, Voronezh — What equipment is used for the production of galvanized steel air ducts?

Stages of constructing a monolithic basement floor

It is more difficult to make a monolithic base, so you need to approach this process very responsibly. Direct construction involves the following actions:

Ground floor arrangement

Installation of formwork. Before starting work, you must make sure that the foundation has gained full strength and is ready for further use. To make formwork, you can use planed boards from which panels are assembled, or you can use ready-made structures

When assembling the shields yourself, you should pay attention to the inside; it should be completely smooth. For this purpose, it is recommended to trim the boards

The formwork elements must be fixed carefully so that the structure does not deform under the influence of the heavy concrete mass. Read about how to choose the right formwork boards.

Base reinforcement. To make the structure stronger, a reinforcement process is necessary. To do this, you must first make reinforcing mesh with a cell size of 15*15 cm, 20*20 cm or 25*25 cm, using steel rods with a diameter of 12 mm. The rods are fastened by welding. The size of the meshes should be slightly smaller than the width of the formwork; the optimal distance from the outer bars of the mesh to the walls of the formwork is 5-10 cm. The number of meshes depends on the parameters of the base; they are located at different levels, 30-50 cm in height.

Pouring concrete mass. You can fill the formwork structure with concrete using the following scheme: first, pour the mortar to a height of up to 15 cm, wait for it to thicken a little, lay the reinforcing mesh, pour the cement mortar again and lay the mesh again. The base, filled according to this scheme, will be durable and reliable.

Operating conditions determine the approach


The technology for laying a brick plinth, as a rule, involves the use of one of the five presented types of clinker (see description in the text)

If we talk about the operating conditions of bricks, they are extremely harsh:

  • firstly, the brick must be very strong - it will have to support the entire building;
  • secondly, the brick must have good frost resistance, because it directly forms the outer wall of the building;
  • thirdly, the brick should not allow moisture to pass through and not be subject to changes under the influence of moisture.

Clinker brick

All these conditions are fully satisfied by clinker bricks, which have:

  • strength - from M75 to M500 (silicate is much inferior here, but acid-resistant is ahead - more than M500);
  • frost resistance - from F50 to F100 (in this indicator, fireclay and acid-resistant are much inferior);
  • average density (kg per cubic meter) – 1900 – 2100;
  • porosity (%) – 5;
  • thermal conductivity coefficient (W per meter) – 1.16.

The next choice is to find the type of clinker brick.

There are five of them mass produced:

  • A – facing;
  • B – construction;
  • C – single;
  • D – one and a half;
  • E – double.

Thus, the most optimal choice is considered to be one-and-a-half clinker bricks with a strength of M400 and frost resistance no worse than F50.

Requirements

In addition, additional requirements are imposed on bricks, taking into account operating conditions:

  • it should not have chips or signs of deformation;
  • its dimensions must exactly correspond to the standards;
  • the brick should not have any claims from an environmental point of view;
  • Cement mortar will be used as a binding material, so it must have good adhesion to the mortar.

Characteristics of the main types of material

At the moment, the industry produces three main types of general construction bricks. Let's consider which of them is most suitable for laying a plinth.

Silicate brick


Sand-lime brick.

  1. The production technology of these products is such that their final price is low. The main disadvantage of the material is that it does not tolerate operation at high humidity. This happens because its basis is lime and sand, produced using the pressing method.
  2. With prolonged exposure to moisture, the elements of silicate masonry absorb it, swell, gradually lose strength and then collapse.
  3. Based on this, making a base from such a material is the least acceptable. The instructions advise using sand-lime bricks in this case only in dry climates and when protecting such plinth masonry with reliable waterproofing.

Clay analogues


Red clay brick.

  1. Unlike its silicate counterpart, ceramic brick is not pressed, but fired. Therefore, this material is more suitable for installing building plinths, because has a higher level of strength, moisture resistance and frost resistance.
  2. However, it also absorbs water well.
  3. Based on this, before laying a plinth made of a brick of this type, select its brand. For example, M-150 products can withstand approximately 50/60 thaw/freeze cycles. If the climate in your region is humid and rainy, it is best to choose the M-250 brand.

Clinker material

Clinker ceramic block.

Another type of ceramic building material is clinker brick. It is this that has the best characteristics for making bases with your own hands. Such products are made from special types of clay, which are fired at very high temperatures.

If you knock on a brick, it will make a thin ringing sound.

  1. The material is not afraid of moisture.
  2. Has a high level of frost resistance.
  3. Has excellent load-bearing capacity.
  4. It is characterized by increased strength.
  5. The brick sizes are standard. This gives the masonry neatness and reduces the labor intensity of the work.
  6. The material has excellent adhesion to the masonry mixture. This prevents the formation of cracks and crevices through which cold and water can penetrate.

Construction of the blind area

Creating a blind area is a mandatory step in the construction of a basement. The fact is that it protects it from the penetration of moisture, namely melt water and precipitation. Its maximum width should be no more than 60 cm, but at least 20 cm higher than the roof extension level.


Construction of the blind area.

Excellent materials for blind areas can be stone, asphalt and concrete. If you are installing it yourself, start from the corners. Treat them with sealant and begin installation.

Work progress

Before starting work, it is necessary to develop discipline for laying bricks.

First choice - masonry scheme

The most common masonry schemes are two chain ligations of corners:

  • a – one brick thick;
  • b – one and a half bricks thick.


Scheme of laying a brick plinth using ligation of corners

The diagram also shows the dimensions of the bricks:

  • 1 – three-four;
  • 2 – half;
  • 3 – four.

Second choice - masonry relative to the wall

Here we have three options:

1 – protruding plinth – the wall of the plinth protrudes forward, outward;

The instructions also determine the order of laying relative to the main wall of the building (see description in the text)

  • 2 – sinking – the base goes back, inward;
  • 3 – base and main wall on the same plane; Note that in the diagram the letters indicate: a – waterproofing;
  • b – wall.

Places where it is intended to use moisture-resistant materials must be equipped with waterproofing layers. When it comes to plinths, there should be two such layers - using one is one of the most common mistakes when building a brick plinth.

The diagram shows two options - correct and incorrect:

on the left - the correct application of waterproofing - two layers, on top and bottom of the foundation plinth;

The cost of laying a brick plinth is also determined by the correct use of waterproofing - it is mandatory to use two layers - on top and bottom of the plinth

on the right - only one layer is used on top.

Work progress

When the installation of the primary strip foundation has been completed, we proceed to laying the bricks:

  • first, the bottom layer of basement waterproofing is laid;
  • then, the angles are set - the most important stage that determines the success of the entire work; to do this: lay out the brick without mortar along the width of the base;
  • to control surfaces we use a level and plumb line;
  • we check that both diagonals and all four corners are identical - maximum deviations should not be more than 2 cm.
  • after leveling, laying is carried out:
  • the solution is prepared from a ratio of 1 to 3 - one part cement and 3 parts sand;
  • each subsequent row is laid with dressing - single-row or chain;
  • longitudinal seams in adjacent rows are shifted by half a brick, transverse seams by a quarter;
  • seams between bricks are made within 10-15 mm;
  • It is strongly recommended that every four rows be reinforced with metal rods or mesh;
  • A layer of waterproofing must be laid on the top surface of the masonry.
  • Insulation of basement brickwork

    Laying bricks must be accompanied by insulation.

    The most commonly used insulation scheme is:

    • A – plaster on the facade of the building;
    • B – brick plinth;
    • C – adhesive layer for insulation;
    • D – insulation in the form of slabs of mineral wool or expanded polystyrene;

    The answer to the question of how much it costs to lay a brick plinth depends not only on the type of brick and work with it - given the strict need for insulation, the cost includes many more materials (see description in the text)

    • E – strengthening solution;
    • F – fiberglass mesh;
    • G – again a solution for strengthening;
    • H – primer;
    • I – finishing plaster on the facade.
    Rating
    ( 2 ratings, average 4.5 out of 5 )
    Did you like the article? Share with friends:
    For any suggestions regarding the site: [email protected]
    For any suggestions regarding the site: [email protected]
    Для любых предложений по сайту: [email protected]