The process of installing a foundation on screw piles with your own hands

The reliability and durability of the entire building depends on the quality of the foundation. Construction of a house on screw piles can be carried out on unstable soils, in a flooded area, on a site with difficult terrain, in seismically active areas.

This technology is one of the most cost-effective. It is quite easy to install screw piles with your own hands. From this article you can glean information on how to properly install screw piles so that the building will serve for many years without repair.

What are screw piles

Screw piles are made in the form of a metal pipe with a tip and screw blades at the bottom. Can be used on difficult soils. They are not suitable for installation on stony and rocky soils, as they will not be able to penetrate a very hard layer when drilling.

The lifespan of a house depends on the correct installation of piles

The dimensions of the supports depend on the mass of the raw materials from which the house will be built and the load-bearing load of building materials, people and objects in the house.

In addition, the calculation takes into account the average mass of the snow layer that may be on the roof in winter.

The service life of the entire building will depend on the correct installation of the pile-screw foundation.

Screwing screw piles is beyond the power of one person; auxiliary workers will be needed to complete the work.

Blade manufacturing process

To make a blade you will need:

  • Sheet steel with a thickness of 5 mm;
  • Plasma cutter and vice;
  • Templates that are necessary for competent marking of the outer and inner diameter of the workpiece;
  • A lever that will be used to stretch the screw spiral (in this case, a simple crowbar can be used).

Blade for screw pile

Where to begin

To determine the type of soil, it is necessary to remove the soil from deep layers.
Before deciding to build a house on stilts, you need to study the condition of the soil and determine the level of groundwater. Such information can be obtained from geodetic, construction organizations or from neighbors who are or have carried out construction.

To independently determine which soil layers lie beneath the construction site, test drilling is carried out. In several places on the site, wells are dug, 1.5 m deeper than the length of the pile. Particles of soil present inside the well remain on the drill blades.

If a flooded area is detected, you need to position the piles for the screw foundation so as to bypass it.

Scope of application

The main provisions and requirements for the design and conditions of use of pile foundations are regulated by SP 24.13330.2011 and SP 50–102–2003. In accordance with these regulatory documents, foundations are designed based on engineering surveys. The main areas of application (the basis for the arrangement) are considered to be the presence of soils on the building site with weak bearing capacity. Such soils include:

  • Loams.
  • Peat bogs.
  • Sandstone.
  • Quicksands.
  • Heaving, vegetative, loess-like soils.
  • Other types of soil with unstable or weak structural connections.

The following factors are also considered the basis for the use of pile foundations:

  • High level of hepatitis B.
  • Swampy area.
  • Seasonal flooding of the area during floods.
  • Seismic activity in the development region.
  • Significant difference in height between the surface of the site.

In addition, the foundation for a building on stilts is organized in cases where the construction of other types of foundations is irrational from an economic point of view. For example, a large volume of excavation work for the construction of a monolithic or slab foundation.

Another area of ​​application for pile foundations is the construction of prefabricated buildings, since the speed of their arrangement allows maintaining a high pace of construction.

Obstacles to installation

Large stones in the soil mean that the place is not suitable for driving piles.
Installation of pile-screw foundations is carried out using a hydraulic apparatus or manually.

Do-it-yourself installation of screw piles is done by screwing in the support like a self-tapping screw.

Obstacles to installing a pile-screw foundation may include:

  • the presence of large cobblestones (more than 5 cm in diameter) or debris in the soil;
  • occurrence of concrete structures from old buildings in the ground;
  • the root system of trees will significantly complicate the screwing of piles;

Manual installation technology involves using a long lever to screw in screw piles. If there is a building, fence, pole or tree close to the installation site of the foundation supports, the lever cannot be rotated 360 degrees. This will serve as an obstacle to constructing a foundation on screw piles.

Recommendations from the pros!

Accessories for a bath Do-it-yourself gazebo Concrete fence Do-it-yourself potbelly stove Do-it-yourself veranda Screw foundation Do-it-yourself country toilet Decorative brick Stone fence Pouring a foundation How to make a fence Wicket from corrugated sheets Do-it-yourself fireplace Brick fence Do-it-yourself flower beds Forged gates Do-it-yourself porch Pool for a bathhouse Chicken coop do it yourself DIY staircase Metal gates Installation of lining Installation of polycarbonate Pump for a summer house Arrangement of a garage Fences for flower beds Do-it-yourself blind area Steam room in a bathhouse Railings for stairs Do-it-yourself cellar Painting walls Press with your own hands Grilles on windows Rolling gates Do-it-yourself barn Alarm system for a summer residence Benches for a summer residence Fence posts Floor screed Solid fuel boilers DIY greenhouse Fence installation House insulation Attic insulation Foundation insulation

Determining the length of the pile

On stable soils, it is enough to screw in the piles to a length of 2.5 m.
The length of the supports used to construct a screw foundation will depend on the soil, the depth of its freezing and the level of the grillage.

If there is stable soil on the site, it will be enough to install supports 2.5 m long. On complex terrain with differences in height, structural elements of various lengths will be needed, depending on the height of the terrain.

On unstable soil, the support should be of such length that it reaches stable, compact soil. Its location is determined by test drilling.

You need to screw in the screw structure to the depth where sand and clay lie. Stable soil will ensure that the load-bearing element is firmly anchored in the soil. The presence of a dense fraction is determined by the particles remaining on the blades.

After this, the depth of the formation is measured. Lower a pebble into the well on a rope until it touches the bottom. Make a mark on the string, lift it and measure the length.

In seismically active areas, the length of the well must be at least 4 m. Supports are purchased half a meter longer than the design ones. It is better to cut off the excess later than during the drilling process it turns out that the length of the pile is not enough.

Stages of performing the required work

Due to the fact that quite a lot of piles are required to build a foundation, it would be impractical to mark each of them using a compass. It is prudent to spend some time making the required templates.

You need to create 2 templates:

  1. A large circle that will have a diameter equal to the outer diameter of the screw;
  2. A small circle with a diameter equal to the outer diameter of the pipe.

It is advisable to mark the central axes on the templates. This will make it easier for you to orient them on the steel strip during the marking process.

After completing the templates, you can proceed to the next stage.

Choosing the right diameter

The diameters of piles produced in production and their purposes are indicated in the table:

DiameterPurpose
15.7 cmSuitable for installing chain-link fences.
27.6 cmThey are used as supports for concrete fences, small utility buildings, and country houses.
38.9 cmSuitable for the construction of one-story houses. One such pile can withstand a load of 3 to 5 tons.
410,8They are used in the construction of two-story houses made of light building materials. A support of this diameter can withstand a load of 5 to 7 tons.

Support design

The support of the designated type is a steel pipe, one part of which is equipped with a spiral blade and a sharp tip. This design allows the installation process to dispense with the use of special equipment to drive the pile into the ground.

Structural elements

The screw support consists of the following elements:


  1. The barrel is a steel profile with a round cross-section.

  2. The tip is the lower part of the pile body, which, due to its pointed shape, more easily overcomes soil resistance.
  3. The blade is a spiral fragment, the configuration of which is determined at the design stage.

Thanks to the presence of a screw fragment, the metal rod is screwed into the ground. At the same time, the soil is further compacted, increasing the bearing capacity of the soil. In the future, the spiral blades will interfere with the forces that push the support outward.

What are the differences between homemade products and factory ones?

The manufacturing process of screw piles is regulated by regulatory documents . In particular, GOST 8732 specifies the requirements for the quality of steel for such supports.

Factory-built products that meet the standards vary in size, configuration, and performance characteristics.

Homemade piles may not have the necessary strength and reliability, so during installation the blades may become deformed or come off.

Pipes made of insufficiently strong steel do not provide the required load-bearing capacity, and a weak waterproofing coating will inevitably lead to premature destruction of the metal by corrosion processes.

Calculation of the mass of the house

Calculate the total weight of all construction and finishing materials that will be used during construction. The estimated maximum weight of furniture, household items, and people who will be in the house are taken into account. Calculate the mass of the bathtub or pool, taking into account that the tank will be filled with water.

Take into account the load of the snow layer that may lie on the roof in winter. This indicator is calculated on the map depending on the region:

Video description

The following video shows in detail the screw manufacturing process:
The finished blade is welded to the end of the pile, trying to ensure that the plane of the screw is perpendicular to the trunk. Apply a suture on both sides, without gaps. The strength of the entire structure depends on its reliability.

Final processing

After completing the welding work, remove scale from the seams and grind them thoroughly. Then the entire product is cleaned of rust, degreased and an anti-corrosion coating is applied. This can be a high-quality metal primer or ship paint. They should be applied in at least two layers, allowing each to dry before applying the next.


Paint will protect metal products from corrosion Source i.ytimg.com

Calculation of the number of piles

The number of supports that will be needed for the foundation will depend on the project and the load-bearing load of the house.

Regulatory requirements:

Material of construction and other factorsDistance between supports
1Frame and wooden housesNo more than 3 m
2House made of foam blocks, gas blocks and other lightweight materialsNo more than 2 m

When carrying out construction in a climate zone with strong winds, the distance between supports is reduced to 2.5 m.

The number of piles is calculated by the formula: add up all possible loads, and divide the resulting value by the load-bearing load of one pile.

Template making process

The process again begins with making a template. It has the shape of a triangle, which is cut out of thin sheet metal or from another (soft) material (for example, plastic or cardboard).

The height of the template should be equal to two pipe diameters.

To determine the size of the template base, you need to perform some calculations:

  1. Carefully calculate the circumference of the trunk section - for this purpose, the outer diameter is multiplied by 3.14;
  2. The result obtained must be divided by the number of sectors from which the cone will be formed. For example, for a pipe with a diameter of 76 mm, 4 will be sufficient.

Based on the results of these simple calculations, we obtain the length of the base of the required triangle - our template.

Rules for placing piles

Piles are placed in the corners of the future structure and in the center of the supporting structures
. Before installing the piles, you need to mark their location on the site. To do this, they initially draw on paper a plan for the placement of supports, guided by the design documentation.

The house plan is divided into rectangles, and the size of each plot is calculated. A pile is placed at each corner of the rectangle and in the center of all supporting structures.

After the location of the supports in areas with the maximum load-bearing load has been determined, the remaining distance between the elements is divided into equal segments. Depending on the estimated number of supports, they are evenly distributed around the perimeter. For more information about the layout, watch this video:

If the project provides for columns or a fireplace, there must be a support under them.

Pile foundation - advantages and disadvantages

The advantages of such grounds include the following aspects:

  • The ability to erect a building in difficult areas when other types of foundations cannot be used.
  • Relatively low labor intensity and high installation speed.
  • Minimizing construction costs, since a pile foundation is considered one of the cheapest options.
  • The absence of excavation work allows you to preserve the natural landscape at the construction site.

Among the disadvantages of this type of foundation, the following factors are noted:

  • The need for calculations, since piles have a limit on their bearing capacity.
  • No basement.
  • This type of foundation is suitable for the construction of relatively light structures.
  • The need to tie the piles, as well as their high-quality waterproofing.
  • The complexity of arranging the floors of the first floor: the use of effective thermal insulation materials is required to prevent freezing.

Do-it-yourself pile installation

To drive the piles, you will need several pairs of working hands.
In small areas, installing a pile foundation using special equipment is unprofitable; it is much more profitable to drive the piles with your own hands.

To do this, you will need a device consisting of a piece of pipe. It should be slightly larger in diameter than the cross-section of the screwed-in support. This pipe must have holes for connecting to the screw structure with bolts and two eyes for installing levers.

You can screw in one support yourself within an hour, depending on the type of soil in the area. You can twist load-bearing elements up to 400 cm in length using the strength of several assistants. Two people will screw in the screw structure, and one should ensure that the vertical plane is maintained using a magnetic level. For detailed instructions, watch this video:

Tools

You will need devices for tightening screw piles:

  • thick-walled pipes with a diameter of 5 cm and a length of 250 cm will be used as levers;
  • tape measure, magnetic level;
  • shovel, crowbar, sledgehammer, hammer;
  • chalk or marker;
  • wooden pegs or reinforcement rods;
  • grinder for cutting piles to height after completion of foundation installation.

Installation technology

Monitor the vertical level of the pile after each turn.
To learn how to install screw piles, you need to study the installation technology. The work is carried out using a twisting device made by hand.

The question often arises of how to tighten screw piles with your own hands so that they do not deviate from the vertical level.

To do this, you yourself need to strictly control the actions of your assistants and the compliance of the screwed-in element with the vertical plane after each 360-degree turn.

After preparing and marking the area, the supports are treated with anti-corrosion compounds. According to the technology, screw piles are first installed in the corners.

Rules for installing piles:

  1. A drill is used to make a hole for mounting screw piles, smaller in width than the diameter of the support. The depth should be 30% of the pile size.
  2. A device is made for screwing screw piles. You need to place a metal element in the prepared hole. A crowbar is installed on the screw piles, inserting it into the technological hole from above. Pipes are placed on the edges of the crowbar, allowing the length of the lever to be extended to 2.5 m. The longer the lever, the easier it will be to screw the support into the soil.
  3. Two people take the levers and tighten the piles by hand. The third holds it in a vertical position and controls after each rotation that the support is immersed strictly at the vertical level.
  4. If the structure cannot be screwed in and loosens the soil, it is loaded. To do this, either two people hang on the levers, or one sits on top. When the screwed-in element rests against a solid object and it is impossible to move it further, leave it as is, and cut off the excess length.
  5. The upper parts are cut horizontally using a laser, bubble level or rangefinder. The technology for installing screw piles involves shortening the length by 100 mm. In some cases, the supports for a screw foundation are shortened by a greater distance.
  6. To impart strength and protect against destruction under the influence of moisture, hollow structures are filled with concrete.
  7. If necessary, a wooden or concrete grillage is built, which serves to uniformly transfer the load from the house to the piles.

When building a house on a pile-screw foundation, you must strictly adhere to the technology of installing screw piles.

Cut the stripes

With the help of competent design of steel strip cutting, the amount of waste can be significantly reduced.

The width and length of the strip must be a multiple of the outer diameter of the blade blank:

  1. It is necessary to lay a large template along the width without any allowances. For example, in the case where we have a diameter of 200 mm, the strip width should be 200 mm;
  2. The strip must correspond in length to the diameter of the template multiplied by the number of blanks (and without any allowances for the gaps between the blanks).

In order for all the blades to be the same size, it is necessary to correctly draw the strip: for this you need to draw the horizontal axis along its length, and the vertical axis, in turn, with a step that will be equal to the diameter of the blade. Moreover, the first vertical must be marked from the short side of the strip at a distance that will be half the diameter of the workpiece.

Using templates, circles are marked. Moreover, these operations can be performed in any order - first large (external), then small (internal) or vice versa.

In the event that you decide not to apply axes to the strip, you need to start marking from the outer contour of the workpiece.

Video description

How to prepare concrete and how to pour piles under the foundation with your own hands is shown in the video:
After the concrete hardens, caps are welded onto the piles - metal platforms on which the grillage will be attached. There are two ways to do this.

  • Weld triangular gussets to the end of the pipe on four sides, and secure the pads to them by welding.
  • Make heads from scraps of pipe of larger diameter, put them on the ends of the piles and weld them in a circle.


Overhead heads with a platform drilled for fasteners Source svai-kirov.ru

Briefly about the main thing

Screw piles consist of a shaft with a sharp tip and a screw. They are made from durable steel and are protected from corrosion by special compounds. In the factory, control is carried out over the manufacturing process, the quality of the materials used and the compliance of finished products with SNiP requirements. It is impossible to recreate the production process at home, since screw piles in this case are made from materials that can be processed manually, that is, less durable. Such products can only be used for the construction of light buildings. They are made from steel pipes, sharpening their lower cut and welding a sheet steel screw to it.

Additionally
The exhibition of houses “Low-Rise Country” expresses sincere gratitude to the specialists for their assistance in creating the material.

(Royal Pile Factory) – expert in pile foundations.

If you need more detailed advice, you can use the following contacts:

website: kzs.ru email: tel.: 8-800-222-76-17

Ratings 0
Read later

Rating
( 2 ratings, average 5 out of 5 )
Did you like the article? Share with friends:
For any suggestions regarding the site: [email protected]
For any suggestions regarding the site: [email protected]
Для любых предложений по сайту: [email protected]